County Highway 12 (Wildwood Road)
During construction, Washington County will send out updates on construction activity. The updates will provide information on work that happened throughout the week and an update on the schedule for the following week. In addition, when applicable, there will be photos, maps, and other information so that residents and business owners can stay informed on the progress.
If you would like to get these updates via email when they are available, sign up by clicking on the button below. All updates will also be posted on this page.
Detours
Construction Photos
Two cameras are placed on-site and take pictures every 12-14 minutes during the entire construction project. This is a great way to view recent activity and the progress throughout construction.
2022 Construction Updates
Washington County has recently taken over jurisdiction of Wildwood Road from Century Avenue to Stillwater Boulevard in the City of Mahtomedi. To continue to make this a great place to live, work, and play, Washington County has a pavement improvement project planned for the near future.
Location
Proposed Improvements
- Pavement replacement
- Replace signing and striping on the roadway
- Improved pedestrian crossings along the corridor
- Signal at Wedgewood Drive
- Multi-purpose off-road trail on a portion of Wildwood Road (on the south side)
- Large culvert replacement within causeway
Pre-construction Open House (April 26, 2022)
Pre-construction Open House Postcard
An online engagement was available for viewing with all of the information that was shared at the in-person open house and provide feedback.
September 7, 2021 City Council Update Presentation
Online Engagement #2 (December 15, 2020)
Information from the Online Engagement:
February 16, 2021 City Council Workshop Presentation
February 16, 2021 Recommended Alternative Layout
Project Process
Open House #1 (March 5, 2020)
Information from the Open House:
DATE | ACTIVITY |
---|---|
Spring 2020 | Public Open House 1 |
Summer 2020 | Begin construction of improved pedestrian crossing just south of the Wedgewood Park Pond |
Fall 2020 | Finish construction of improved pedestrian crossing just south of the Wedgewood Park Pond |
Winter 2020 | Public Open House 2 |
2021 | Detailed design and right-of-way acquisition |
Spring 2022 | Pre-Construction Public Open House |
Spring 2022 | Begin construction of corridor pavement improvement, and culvert replacement |
Spring 2023 | Finish construction of corridor pavement improvement, and culvert replacement |
-
Allan Brandt
Construction EngineerPhone: 651-430-4348
-
Kevin Peterson
Project ManagerPhone: 651-430-4330
-
Mindy Leadholm
Right of Way SpecialistPhone: 651-430-4361