Schedule

 DATE  ACTIVITY
October 4, 2016 Open House #1
Summer 2016 - Spring 2017 Preliminary Design
April 6, 2017 Open House #2
2017 Final Design and Acquisition Process
Spring 2018 Construction Begins
Fall 2018 Construction Substantially Complete